NTPL Thermal Power Station
NTPL Thermal Power Station is a 1000 MW (2×500 MW) coal-based thermal plant in the Tuticorin District of Tamil Nadu. The project is a joint venture of TANGEDCO and NLC India Limited. The units were commissioned in March and April 2015, respectively.[1]
| NTPL Thermal Power Station | |
|---|---|
| Location of the NTPL Thermal Power Station | |
| Country | India | 
| Location | Harbour Estate, Thoothukudi, Tamil Nadu | 
| Coordinates | 8°45′32″N 78°10′54.8″E | 
| Status | Operational | 
| Commission date | Unit 1: March 2012 Unit 2: August 2012 | 
| Owner(s) | |
| Operator(s) | TANGEDCO, NLC India Limited | 
| Thermal power station | |
| Primary fuel | Coal | 
| Power generation | |
| Units operational | 2 X 500 MW | 
| Nameplate capacity | 1000 MW | 
| External links | |
| Website | www | 
References
    
-  
- Broad Status Report, Archived 2012-05-10 at the Wayback Machine India Central Electrical Authority, February 2015
- "It is a victory for people of Uttara Kannada district: Hanakon plant shifted to Tuticorin", Deccan Herald, January 2, 2010.
 
    This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.