Woolloongabba railway station is a railway station currently under construction as part of the Cross River Rail project in the Brisbane suburb of Woolloongabba.

Woolloongabba
Woolloongabba railway station under construction in February 2021
General information
LocationMain Street, Woolloongabba
Owned byQueensland Rail
Operated byQueensland Rail
Line(s)Cross River Rail
Platforms2
Tracks2
ConnectionsBus
Construction
Structure typeUnderground
AccessibleYes
Other information
StatusUnder construction
Fare zoneGo card zone 1
Websitewww.crossriverrail.qld.gov.au
History
Opened2026 (scheduled)
ElectrifiedYes

To be built as an underground station beneath The Gabba, it will consist of two platforms with a connection to Woolloongabba busway station.[1] Construction commenced in November 2019, with it scheduled to open in 2026.[2] The platforms are built at a depth of 27 metres.[3] Their length is 220 metres.

Construction

The station is built using a full cavern construction method.[3] It was important to design lifts and elevators that can handle the expected surge capacity during large sports events at the nearby Gabba.[3] Similar to Boggo Road railway station the ground is heavily fractured, but at Woolloongabba the cavern sits underneath a layer of that kind of rock. The cavern was excavated using roadheaders.[3]

During construction a toothpaste box, a perfume bottle and bottles that once contained alcohol as well as other food items were found.[4] Animal bones, including pig, sheep goats and cows and pieces of leather from shoes, shoe soles, leather belts and off cuts were also discovered.[5]

The station served as the main support site for the construction project.[6] It was centrally located and had adequate space for materials that created handling and logistical support efficiencies.[6] The site handled the majority of spoil handling movements,[6] having good access to the Pacific Motorway.

The first of several escalators were installed by September 2023, marking the move to the mechanical and electrical fit out phase of construction.[7] A total of 24 escalators will be installed.[7]

See also

References

  1. Woolloongabba Station Cross River Rail
  2. Moore, Tony (1 April 2023). "Bailey defends $960 million Cross River Rail cost blowout, delays". Brisbane Times. Retrieved 17 April 2023.
  3. Claire Smith. "Future of Tunnelling: Using caverns to minimise tunnelling disruption in Brisbane". EMAP Publishing. Retrieved 22 October 2021.
  4. George Roberts (3 November 2019). "Archaeologists find Queen Victoria-inspired perfume under future Woolloongabba Cross River Rail station". Retrieved 22 October 2021.
  5. Digging Deeper: The Lifecycle of a Leather Shoe. Cross River Rail. 2 September 2021. Retrieved 23 October 2021.
  6. "Cross River Rail Business Case August 2017" (PDF). Government of Queensland. p. 108. Retrieved 23 October 2021.
  7. Cook, Kody (11 September 2023). "Cross River Rail underground stations reach milestone". Infrastructure Magazine. Retrieved 13 September 2023.