Snowy 2.0 Pumped Storage Power Station
Snowy 2.0 Pumped Storage Power Station or Snowy Hydro 2.0 is a pumped-hydro battery megaproject in New South Wales, Australia. The dispatchable generation project connects two existing dams through a 27-kilometre (17 mi) underground tunnel and a new, underground pumped-hydro power station.[2] Construction began in 2019.[2] It is expected to supply 2.2 gigawatts of capacity and about 350,000 megawatt hours of large-scale storage to the national electricity market.[3][4] It is the largest renewable energy project under construction in Australia.[5]
Snowy 2.0 Pumped Storage Power Station | |
---|---|
Country | Australia |
Location | Snowy Mountains |
Status | Under construction |
Construction began | 2019 |
Construction cost | AUD 12 billion[1] |
Owner(s) | Snowy Hydro |
External links | |
Website | https://www.snowyhydro.com.au/ |
It is designed for grid stabilization; to be a backup at times of peak demand and for when solar and wind energy are not providing power.[6] Snowy Hydro acts like a giant battery by absorbing, storing, and dispatching energy.[3] The battery is designed to operate for up to 175 hours of temporary supply.[7] It is Australia's largest energy project,[8] estimated to cost 12 billion Australian dollars. By 2023, AU$4.3 billion had been spent.[1] The project is led by public company Snowy Hydro Limited.[8] When complete it is expected to have a large impact on the price and reliability of electric power.[9]
History
Initial plans for a power station at the location were discussed in 1966.[10] Further studies were undertaken in 1980 and 1990.[10] The current project originated as the centrepiece of Malcolm Turnbull's climate change policy in 2017.[11] A feasibility study carried out in 2017 finding the project was both technically and financially feasible.[10] The study was released on 21 December 2017 and found the project cost would be between $3.8 and 4.5 billion.[12]
The first tunnel that was completed by October 2022, was a 2.85 kilometre section that provided main access at Lobs Hole.[13] It was 10 metres in diameter and provides pedestrian and vehicle access into the power station.[13] By May 2023 the emergency, cable and ventilation tunnel was excavated.[14] It is 2.93 kilometre long, 10 metres in diameter and will be used for power station ventilation and high-voltage cables.[14]
It was originally expected to be completed by 2024.[15][16] Snowy Hydro 2.0 has been beset by delays and cost blowouts.[11][6][4] Delays have been caused by the COVID-19 pandemic, global supply chain disruptions, complex design elements and variable site and geological conditions.[7] The delays have raised concerns that Snowy Hydro will not be ready in time for new solar and wind projects coming online as five coal-fired power stations close.[6] AEMO warns that supply gaps will emerge from 2025.[4] The project is currently expected to be fully operational by the end of 2028 and generating power as early as late 2027.[5]
The project is using three tunnel boring machines to dig tunnels.[11] One of the machines, called Florence was stuck for 19 months after encountering soft rock near Tantangara.[16] Florence launched in March 2022. Eight weeks later the machine was bogged in wet soft ground. The machine is capable of digging 30 to 50 metres a day. In December 2022, a sinkhole opened up above the tunnel.[16]
Design and location
It is located remotely within the Kosciuszko National Park in the Snowy Mountains.[3] Snowy Hydro 2.0 will use water from the Talbingo Reservoir (bottom storage) and Tantangara Reservoir (top storage).[9] The new power station is being built by the Italian firm Webuild.[17] It will be located in a cavern 800 metres underground.[9] The underground location allows for reduced environmental impacts within the national park. The operational footprint of the facility is less than 0.01% of the total size of the park.[18]
The power station will measure 22 metres (m) wide, 50 m high and 250 m long.[8] The station will house six reversible Francis pump-turbine and motor-generator units.[15] Three units will be of variable speed with the remaining of synchronous speed. Each turbine will have a rated output of 333 megawatts.[19] Power generating equipment is being supplied by Voith.[19]
It will be connected to the grid via the HumeLink transmission line.[11][20] The construction of overhead power lines by TransGrid has been opposed by community advocacy groups.[21] Landholders desire to see the transmission line built underground have been opposed due to prohibitive costs.[21]
See also
References
- Vorrath, Sophie (31 August 2023). "Bowen confirms $12bn Snowy 2.0 cost blowout, says pitfalls should have been known". RenewEconomy.
- "History". Snowy Hydro. Retrieved 5 May 2023.
- "The next generation of hydropower in Australia". SMEC. Retrieved 5 May 2023.
- Morton, Adam; Rose, Tamsin; Hannam, Peter (3 May 2023). "Snowy Hydro 2.0 project hit by delay of up to two years and another cost blowout". The Guardian. Retrieved 5 May 2023.
- Lowrey, Tom (31 August 2023). "Snowy Hydro expansion hits reset button as costs blow out to $12 billion". ABC News. Retrieved 24 October 2023.
- Toscano, Nick; Foley, Mike (3 May 2023). "Snowy 2.0 pumped hydro project hit with new delays, cost blowouts". The Sydney Morning Herald. Retrieved 5 May 2023.
- "Timeline, budget reset for Snowy 2.0 pumped storage". Hydro Review. 5 April 2023. Retrieved 5 May 2023.
- "Snowy 2.0: A pumped-storage plant of colossal proportions". Tractebel. 20 July 2022. Retrieved 5 May 2023.
- Ziffer, Daniel (6 January 2023). "Snowy Hydro could change our electricity grid and bring cheap power. But we have to build it". ABC News. Australian Broadcasting Corporation. Retrieved 5 May 2023.
- Cella, Lauren (24 January 2020). "Snowy 2.0 underway". Pump Industry. Retrieved 5 May 2023.
- Dhanji, Krishani (3 May 2023). "Snowy Hydro 2.0 pumped-hydro battery project faces a further two years of delays". ABC News. Australian Broadcasting Corporation. Retrieved 5 May 2023.
- "Snowy 2.0 feasibility study released". ARENA. Retrieved 5 May 2023.
- "Milestone first tunnel completed for Snowy 2.0". Snowy Hydro. 11 October 2022. Retrieved 5 May 2023.
- Eastaway, Gail (26 May 2023). "Tunnel vision turns to reality in Snowy Hydro 2.0 milestone". Riotact. Retrieved 26 May 2023.
- "Snowy 2.0 Hydropower Project, New South Wales". PowerTechnology. Verdict Media. Retrieved 5 May 2023.
- Grigg, Angus; Robinson, Lesley; Gock, Kamin. "A sinkhole, toxic gas and the $2 billion mistake behind Snowy 2.0's blowout". ABC News. Retrieved 23 October 2023.
- "Snowy 2.0 : Webuild Group". Webuild. Retrieved 24 October 2023.
- "FAQs". Snowy Hydro. Retrieved 5 May 2023.
- "Voith Snowy 2.0". ICN Gateway. Retrieved 5 May 2023.
- "HumeLink inches ahead as state inquiry rules out putting lines underground". RenewEconomy. 31 August 2023.
- Burke, Conor (31 August 2023). "Inquiry deems Transgrid's HumeLink energy transmission project will remain above ground". ABC News. Retrieved 25 October 2023.