The Civil Engineering Standard Method of Measurement (commonly known as CESMM3) sets out a procedure for the preparation of a bill of quantities for civil engineering works, for pricing and for expression and measurement of quantities of work.
CESMM3 includes 26 main clauses of work:
| Class | Description | 
|---|---|
| A | General Items | 
| B | Ground Investigation | 
| C | Geotechnical & other specialist process | 
| D | Demolition and Site Clearance | 
| E | Earthworks | 
| F | In situ Concrete | 
| G | Concrete ancillaries | 
| H | Precast Concrete | 
| I | Pipework - Pipes | 
| J | Pipework - Fittings and valves | 
| K | Pipework - Manholes and pipework ancillaries | 
| L | Pipework - Supports and protection, ancillary to laying and excavation | 
| M | Structural Metal works | 
| N | Miscellaneous Metal works | 
| O | Timber | 
| P | Piles | 
| Q | Piling ancillaries | 
| R | Roads and pavings | 
| S | Rail Track | 
| T | Tunnels | 
| U | Brickwork, block work and masonry | 
| V | Painting | 
| W | Waterproofing | 
| X | Miscellaneous works | 
| Y | Sewer and water main renovation and ancillary works | 
| Z | Simple building works incidental to civil engineering works | 