Boundary Dam Power Station

Boundary Dam Power Station is the largest coal fired station owned by SaskPower, located near Estevan, Saskatchewan, Canada.

Boundary Dam Power Station
CountryCanada
LocationEstevan No. 5, near Estevan, Saskatchewan
Coordinates49°5′47″N 103°1′49″W
StatusOperational
Commission date1959
Owner(s)SaskPower
Thermal power station
Primary fuelCoal (lignite)
Turbine technologySteam turbine
Power generation
Nameplate capacity531 megawatts

Description

The Boundary Dam Power Station consists of[1] two 62 net MW units (commissioned in 1959, shut down and decommissioned in 2014[2]); two 139 net MW units (commissioned in 1970), one of which—Unit 3—was decommissioned and replaced with a new 160 MW unit in 2013;[3] one 139 net MW unit (commissioned in 1973); and one 273 net MW unit (commissioned in 1978).

The boilers are supplied by Babcock & Wilcox and Combustion Engineering while the turbines/generator are supplied by General Electric and Hitachi.[4] There is also Boundary Dam (constructed in 1957) located next to the station. It is an earth fill dam, which created the Boundary Dam Reservoir on Long Creek a few kilometres west of the river's mouth on the Souris River. The station uses water from the reservoir for coolant, which is why Boundary Reservoir is the only body of water in Saskatchewan that doesn't freeze over during the winter months and supports largemouth bass.[5]

The plant has five 300 ft (91.44 m) tall smokestacks.[6] SaskPower has advised that the project has a 30-year life.[7]

Carbon capture and storage demonstration project

The Boundary Dam Integrated Carbon Capture and Storage Demonstration is a project to retrofit the lignite-fired Unit #3 with a carbon capture system.[8][9][10] It consists of two distinct parts: Repowering of the existing Unit #3 and the installation of the carbon dioxide, sulfur dioxide and NOx capture facility.[11] Its primary purpose is to provide a low-cost source of carbon dioxide, to the mature Weyburn Oil Field, for enhanced oil recovery.[12][13] It is expected to result in a 90 percent (1 million tonnes/year) reduction in CO2 emissions and will also reduce the output of Unit 3 from 139 MW to 110 MW.[14] Critics point out that the 90% figure refers to the percentage of total CO2 emissions captured, and that only about a half of this CO2 will actually be permanently stored. The remainder is released into the atmosphere during capturing and processing in the oil field.[15] The retrofitted unit was officially opened in October 2014,[16] and is the world's first commercial-scale, lignite-fired power plant equipped with carbon capture and storage technology[17][18]

In 2015, internal documents from SaskPower revealed that there were "serious design issues" in the carbon capture system, resulting in regular breakdowns and maintenance problems that led the unit to only be operational 40% of the time. SNC-Lavalin had been contracted to engineer, procure, and build the facility, and the documents asserted that it "has neither the will or the ability to fix some of these fundamental flaws."[19] The low productivity of the plant had in turn meant that SaskPower was only able to sell half of the 800,000 tonnes of captured carbon dioxide that it had contracted to sell to Cenovus Energy for use in enhanced oil recovery at a cost of $25 per tonne. In addition to the lost sales, this meant that SaskPower had been forced to pay Cenovus $12 million in penalties.[20] In June 2016, and to avoid paying a $91-million penalty, SaskPower renegotiated its CO2 supply contract with Cenovus. That renegotiation means annual revenues are reduced from $25 million to "$16-17 million". Over the 30-year project life this represents reduced revenue of $240 million to $270 million and will further weaken the project economics.[21] Cenovus sold its Saskatchewan interests in 2017 to Whitecap Resources.[22]

Several major publications have noted what they deem poor economics of the project, among them The Economist,[23] The Financial Times,[24] The MIT Technology Review,[25] and The New York Times.[26][27] An April 2016 Parliamentary Budget Office report found that CCS at Boundary Dam doubles the price of electricity.[28]

Financial concerns appear to fall into three main areas:

Among environmental concerns, critics note that while 90% of CO2 smokestack emissions are captured, only a portion is stored. Almost half of captured emissions end up being released in the atmosphere by processing in the oil field and the capturing process.[33]

Among other concerns, critics point to the following:

  • The foremost goal of the CCS project is to keep the aging plant from becoming a stranded asset.
  • The unfair sharing of the costs, risks and benefits: Energy consumers are said to be saddled with a "very expensive carbon tax", while Saskatchewan's aging oil industry, namely Weyburn Consortium (formerly headed by Cenovus Energy), which owned the Weyburn oil field until it was sold in 2017[22] receives a "backdoor subsidy."[15][34]

All of these concerns are compounded by a lack of transparency: As of 2015 the project operators had not presented any financial or environmental performance numbers.

In July 2018, SaskPower announced that it would not retrofit Units 4 and 5 with CCS, with minister responsible Dustin Duncan saying that the units were approaching their mandated shut down in 2024 and that natural gas is a cheaper option.[35]

Capital cost

In February 2008 the Saskatchewan government announced that it would proceed with a 7-year reconstruction and repowering of Boundary Dam's Unit 3. The initial project cost was C$1.24 billion[36] out of which C$240-million was from the federal government.[14][37] Budget over-runs have led to the plant having a total cost of some $C 1.5 billion.[38][39]

Revenue

Other than the generation of electricity, the plant will have several by-products which will generate revenue.

Sample of solid carbon dioxide or dry ice pellets

Carbon dioxide

The facility planned to capture 90 percent of total carbon dioxide emissions from Unit 3[40] or one million tonnes annually.[41] However reports state that less than 90% of total carbon dioxide emissions are being captured.[42] [43]

Most of the total annual carbon dioxide capture volume, at least for the first ten years of the project, was sold to Alberta-based Cenovus Energy,[44] the operator of the Weyburn Oil Field.[45] SaskPower has not publicly disclosed the sale price but Minister Boyd has stated that it is "in the range of" $25 per tonne.[46] Annual revenue from carbon dioxide sales is thus estimated at $25 million. Cenovus Energy used the carbon dioxide mainly for field injection work to increase crude oil production before its Saskatchewan operations were sold to Whitecap Resources.[22]

Sulfuric acid

Most of the sulfur emissions from the power station (predominantly sulfur dioxide) will be captured,[40] converted to sulfuric acid and sold. SaskPower sulphur dioxide emissions are approximately 5 tonnes per gigawatt hour of system generation.[47] Given annual electricity generation of 1,010 gigawatt hours, it follows that total annual sulfur capture will be 5,050 tonnes.

Fly ash

Fly ash, also known as flue ash, is one of the residues generated following the combustion of coal and lignite. In the past it was released into the atmosphere through the smoke stack but pollution control requirements have put an end to that practice. It is now captured by electrostatic precipitators and stored at the point of generation, placed in landfills or recycled - where it will typically replace Portland Cement in concrete production. Typical fly ash recovery rates, for Saskatchewan lignite-fired power stations, are 31 kilograms per megawatt hour.[48] Fly ash, depending on its use, can attract a range of prices. The best arises from concrete-quality ash which fetches $22–$49 per tonne.[49]

Expenses

There appear to be two main expense items: Operations and maintenance, and parasitic load. In the latter, carbon and sulfur dioxide amine-based capture units, such as the one at Boundary Dam, consume significant amounts of electricity and heat in operation and the largest single component is associated with solvent regeneration.[50] Significant electrical load is also used to run additional emission control components (e.g. NOx and mercury capture) as well as associated pumps and other equipment.

See also

References

  1. "Plant Description". Archived from the original on 2010-01-05. Retrieved 2010-01-17.
  2. "BD3 project readied for launch". Estevan Mercury. Retrieved 25 December 2018.
  3. "Alberici to install turbine for SaskPower carbon capture facility."Electric Light & Power. 1 September 2013
  4. "Coal Fired Power Plants in Canada - Power Plants Around the World". Archived from the original on 2012-12-05. Retrieved 2010-04-21.
  5. Snook, M., "Saskatchewan's Best Fishing Hot Spots Archived 2014-12-20 at the Wayback Machine", Western Sportsman. 22 June 2011. Retrieved 20 December 2014.
  6. "Boundary Dam Power Station". Environment Canada - Detailed Facility Information.
  7. "Hanley: Questions remain over SaskPower project." The Star Phoenix - 18-Nov-2014.
  8. "HOW TO DECARBONISE COAL-FIRED POWER PLANTS" (PDF). OECD 13th Plenary Meeting of the Policy Dialogue on Natural Resource-based Development. 25 November 2019.
  9. Anderson, Drew (24 January 2022). "Governments are investing billions into carbon capture in the Prairies. Here's what you need to know". The Narwhal.
  10. Boundary Dam Integrated Carbon Capture and Storage Demonstration Project
  11. Danko, Pete (2 October 2014). "World's First Full-Scale 'Clean' Coal Plant Opens in Canada". National Geographic Society.
  12. "Boundary Dam Integrated Carbon Capture and Sequestration Demonstration Project Archived 2014-08-10 at the Wayback Machine" Global CCS Institute
  13. "Integrated Carbon Capture & Storage Project at SaskPower's Boundary Dam Power Station" Global CCS Institute 2015
  14. "Sask. going ahead with $1.2B carbon capture project | CBC News".
  15. "Turns out the world's first "clean coal" plant is a backdoor subsidy to oil producers". 31 March 2015.
  16. "404". {{cite web}}: Cite uses generic title (help)
  17. "SaskPower unveils world's first carbon capture coal plant". Shawn McCarthy. Globe and Mail. 2-Oct-2014
  18. "SaskPower launches world's first commercial CCS process." SaskPower News release. 2-Oct-2014
  19. Leo, Geoff (October 27, 2015). "SNC-Lavalin-built carbon capture facility has 'serious design issues': SaskPower". CBC News. Retrieved 22 November 2015.
  20. Leo, Geoff (October 26, 2015). "Carbon capture plant delay costing SaskPower millions". CBC News. Retrieved 22 November 2015.
  21. "SaskPower renegotiated contact to avoid $91.8M penalty." The Leader Post. 13-Jun-2016.
  22. "Cenovus selling majority stake in Weyburn oil project". CBC News. November 13, 2017. Retrieved January 29, 2018.
  23. "Nice try, shame about the price." The Economist. 3-Oct-2014
  24. "Carbon Capture Faces Viability Struggle." Pilita Clark. Financial Times. 23-Nov-14.
  25. "A coal plant that buries its greenhouse gases" Archived 2015-12-22 at the Wayback Machine. Peter Fairley: MIT Technology Review. Dec-2014.
  26. "Corralling Carbon Before It Belches From the Stack".Henry Fountain: The New York Times. 21-Jul-2014.
  27. Companies Struggle To Make Carbon Capture Viable Mark Scott. New York Times. 5-Oct-2015
  28. "Sask. carbon capture plant doubles the price of power." Stefani Langenegger. CBC. 17-Jun-2016
  29. "Carbon Capture faces viability struggle." Pilita Clark. Financial Times. 23-Nov-2014
  30. http://www.saskwind.ca/wind-atlas-skthe highest power-sector carbon
  31. "Push for CCS misguided policy." Archived 2014-12-11 at the Wayback Machine Letters - James Glennie. The Star Phoenix. 28-Mar-2014.]
  32. "CO2 project sequesters tax dollars" Archived 2014-12-09 at the Wayback Machine. Murray Mandryk. The Leader Post: 7-Oct-2014
  33. "Study: Boundary Dam CCS".
  34. ""CO2 project sequesters tax dollars"". Archived from the original on 2014-12-09. Retrieved 2014-12-07.
  35. "No more retrofits for carbon capture and storage at Boundary Dam: SaskPower". The Province. 2018-07-09. Retrieved 2018-07-10.
  36. "Boundary Dam Integrated Carbon Capture and Storage Demonstration Project". SaskPower Fact Sheet: 7211/Apr12
  37. "Saskatchewan Plans Clean Coal-Carbon Capture Project." 27-Feb-2008. Power Engineering
  38. "CCS Performance Data Exceeding Expectations at World-First Boundary Dam Power Station #3". SaskPower press release. 11-Feb-2015.
  39. "Jim Prentice says to wind down carbon capture fund in Alberta, new projects 'on hold'". Geoffrey Morgan - Financial Post. 6-Oct-2014.
  40. "SaskPower Boundary Dam Project" Carbon Capture Journal. July–August 2010
  41. "Boundary Dam Integrated Carbon Capture and Storage Demonstration Project." SaskPower fact sheet. 7211/Apr12.
  42. "Only still-operating carbon capture project battled technical issues in 2021". www.spglobal.com. Retrieved 2023-05-20.
  43. Anchondo, Carlos (2022-01-10). "CCS 'red flag?' World's sole coal project hits snag". E&E News. Retrieved 2023-05-20.
  44. "SaskPower signs 10-year deal with Cenovus Archived 2014-12-11 at the Wayback Machine" Bruce Johnstone Leader-Post. 20-Dec-2012
  45. "Increasing oil production and reducing greenhouse gas emissions." Archived 2014-12-22 at the Wayback Machine 'Weyburn Project Overview' - Cenovus Energy fact sheet
  46. ". Legislative Assembly of Saskatchewan - Debates and Proceedings. Page 5836. Minister Bill Boyd response to question from MLA Cathy Sproule". Hansard 13-Nov-2014
  47. SaskPower Sustainability Report 2011. (no longer available on SaskPower site)
  48. Reference withheld at author request.
  49. "How Much are Coal Combustion Products Worth?" The American Coal Ash Association Website.
  50. "Cansolv CO2 Capture: The Value of Integration Archived 2014-12-09 at the Wayback Machine" Devin Shaw. Cansolv Technologies Inc. Oct-2008. Shell website
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.